The Rain Bridge
Design and build, timber footbridge
- Location
- CAT, Machynlleth, Powys
- Sector
- Education, live build
- Year
- 2022 to 2023
- RIBA stage
- 2 to 5, built
- My role
- Design and build, team of five
The old footbridge at the heart of the Centre for Alternative Technology had rotted beyond repair. The brief was to replace it for £1,000, with one week on site. It had to last in the Welsh climate, add to the visitor experience and sit with the Japanese-influenced buildings around it.
The answer was a covered bridge, designed and built by five MArch students: Nina Xenitidou, Chris Da Costa, Waldo Olwage, Becca Illingworth and me. The roof keeps the structure dry, and a gap in the corrugated steel valley roof drops rainwater through an opening in the deck to the plants below. You hear the rain on the roof, smell it, and can run your fingers through it as you cross.
We developed the design with an engineer, a master builder, a carpenter and a timber specialist. Then we built it ourselves, raising the frame in a single build week in summer 2022 and finishing the bridge in 2023.
From proposal to build
Each of us first developed our own proposal. A beam check on mine showed the two donated Douglas fir beams were under strength for the span, so I designed around a truss. The group then took Nina’s rain bridge forward together.
Development focused on stiffening those beams and keeping the timber dry. Scissor truss frames replaced a simple post and beam. They give the roof its winged shape, resist wind uplift and carry the valley gutter, while a timber queen post truss stiffens the deck. Douglas fir felled nearby was milled on site and stacked to dry. A full cutting list and naming system meant every piece could be identified on site.